Twenty poles, five utilities, four weeks
A gas utility committed to installing AMI meter-reading radios across Western Washington and needed approvals for 20 pole attachments spanning multiple electric utilities and jurisdictions, on a four-week clock. Our team delivered every submittal package on time.

FIELD TO SUBMITTAL, FAST
Immediate field data collection at each location, followed by pole loading and clearance analysis and the drawings each jurisdiction required for approval.

Twenty poles, five utilities, four weeks. Joint use rewards the prepared.
BOTTOM LINE
- A client needed twenty jurisdiction-ready packages in a month.
- Our team collected, analyzed, and shipped all twenty.