Skip to content

A greenfield substation, delivered on plan

An electric cooperative is building a new 115 kV substation, plus the transmission and distribution work around it, to serve fast-growing load. They needed one firm keeping design, procurement, and construction moving as a single program. Our team serves as the owner’s program manager and engineer.

Foundations and steel stubs across the yard, August 2026.
Foundations and steel stubs across the yard, August 2026.

WHAT WE CARRY

The board sees where every dollar and every week stands, reconciled to the penny, every month.

Transformer foundation cured and ready for the fall set.
Transformer foundation cured and ready for the fall set.

WHERE IT STANDS

Foundations are in, steel is standing, and the transformer sets this fall. The program is tracking to an energization target of year end.

BOTTOM LINE

  • A client needed a substation built without surprises.
  • Our team runs the program like the money is our own.

Ten feeders, eight breakers, zero surprises

Golden hour on the 115 kV yard, energized and carrying load.
Golden hour on the 115 kV yard, energized and carrying load.

A public utility district built a new 115 to 12.47 kV substation with an 8-position ring bus and ten feeder getaways. Our team provided the owner’s commissioning: relay testing, design review, drafting, and the troubleshooting that keeps an energization date honest.

RELAY AND CT TESTING

We wrote the relay test plans, then performed relay testing, logic verification, and current transformer testing at every position.

Panel wiring, dressed and verified point by point.
Panel wiring, dressed and verified point by point.

DESIGN REVIEW

Acting as the client’s engineer, we reviewed and corrected relay design submittals, calculations, time-current coordination, logic packages, and controller settings before they reached the field.

On a ring bus, one unverified interlock does not cause an outage. It causes a sequence of them.

COMMISSIONING

We developed and ran commissioning procedures for batteries, breakers, LTCs, logic schemes, SCADA, and the power transformers, through energization.

Site acceptance, panel by panel.
Site acceptance, panel by panel.

BOTTOM LINE

  • A client needed a complex substation proven before it carried load.
  • Our team tested every trip path and signed our name to the results.

Taylor Flats: control house, 25 MVA transformer, five reclosers

Court Street substation rebuild in-place

25 MVA mobile substation

Foster Wells Bay 3 transformer replacement

Snake River substation — all relays replaced

Substation planning estimate, 115–12.47 kV addition