Skip to content

← Back to the system

FLAGSHIP · 2025

Ten feeders, eight breakers, zero surprises

Client
Public utility district, WA
Role
Commissioning engineer
Scope
New substation + feeders
Status
Complete
Golden hour on the 115 kV yard, energized and carrying load.
Golden hour on the 115 kV yard, energized and carrying load.

A public utility district built a new 115 to 12.47 kV substation with an 8-position ring bus and ten feeder getaways. Our team provided the owner’s commissioning: relay testing, design review, drafting, and the troubleshooting that keeps an energization date honest.

RELAY AND CT TESTING

We wrote the relay test plans, then performed relay testing, logic verification, and current transformer testing at every position.

Panel wiring, dressed and verified point by point.
Panel wiring, dressed and verified point by point.

DESIGN REVIEW

Acting as the client’s engineer, we reviewed and corrected relay design submittals, calculations, time-current coordination, logic packages, and controller settings before they reached the field.

On a ring bus, one unverified interlock does not cause an outage. It causes a sequence of them.

COMMISSIONING

We developed and ran commissioning procedures for batteries, breakers, LTCs, logic schemes, SCADA, and the power transformers, through energization.

Site acceptance, panel by panel.
Site acceptance, panel by panel.

BOTTOM LINE

  • A client needed a complex substation proven before it carried load.
  • Our team tested every trip path and signed our name to the results.